When trying to perform an initial Test migration (no upgrade or other options), receive error message about insufficient cores!

Neal Eckett 20 Reputation points
2024-04-29T15:13:04.3633333+00:00

When trying to perform initial test migration, receive the following message:

Sufficient number of cores are not available in the subscription xxxxxxxx in the region uksouth to complete migration. Number of cores required to complete migration: 13. Number of cores available in the subscription: 10. I have checked to see if there is a limitation within the subscription, but cannot see any! I cannot believe that uksouth does not support that many! Any help appreciated.

Thanks

Azure Migrate
Azure Migrate
A central hub of Azure cloud migration services and tools to discover, assess, and migrate workloads to the cloud.
732 questions
{count} votes

Accepted answer
  1. TP 79,341 Reputation points
    2024-04-29T15:25:20.9933333+00:00

    Hi Neal,

    Please check and increase Quotas as needed so that you have enough to complete the migration. There are two you need to check, one for the specific instance family size for uksourth and one for Total Regional vCPUs for uksouth.

    Below is the link to where you can view and request increase of Quotas:

    https://portal.azure.com/#view/Microsoft_Azure_Capacity/QuotaMenuBlade/~/myQuotas

    Please click Accept Answer and upvote if the above was helpful. If you are unsure add a comment and I will assist further.

    Thanks.

    -TP

    1 person found this answer helpful.
    0 comments No comments

0 additional answers

Sort by: Most helpful