Allocate time to jobs in a job bundle

In Manufacturing execution, you can bundle jobs. You can then start multiple jobs at the same time on the Job list page.

If you bundle jobs, you must define how the total registered time for all the jobs should be allocated to each job. You define the allocation by selecting one of the following options in the Bundle type field on the Allocation keys page:

  • Estimation – Time is divided among the jobs, based on the estimated time for the jobs.
  • Jobs – Time is divided according to total jobs that are bundled and how much time was spent finishing all the jobs.
  • Net time – Time is divided equally among the jobs that are in the bundle at any time.
  • Real time – Actual job time is allocated. The cost can be calculated based on the actual payroll cost. Note: The Real time allocation key is available only if your company uses the payroll functionality in Time and attendance.

The following examples show the results of the various allocation keys.

Example scenario

Three jobs in your job queue must be completed. You start the first job, and then, while that job is in progress, you start the second and third jobs. Therefore, there is a bundle of three jobs. The following table shows the estimated production time for each job.

Job Production time
Job 1 1 hour
Job 2 3 hours
Job 3 4 hours
Total 8 hours

The following table shows the actual work hours that are spent on each job.

Job Start time End time Bundle time
Job 1 09:00 11:00 2 hours
Job 2 10:00 13:00 3 hours
Job 3 10:00 15:00 5 hours
Bundle 09:00 15:00 6 hours

The following sections describe the results of the calculated time for each allocation key.

Estimation allocation key

The following table illustrates the formula for calculating allocated time. Here is the formula: Time per job = Total bundle time × (Estimated job time ÷ Total estimated time)

Job Formula Allocated time
Job 1 6 × (1 ÷ 8) hours 0.75 hour
Job 2 6 × (3 ÷ 8) hours 2.25 hours
Job 3 6 × (4 ÷ 8) hours 3.00 hours

Jobs allocation key

The following table illustrates the formula for calculating allocated time. Here is the formula: Time per job = Total bundle time ÷ Number of jobs

Job Formula Allocated time
Job 1 6 ÷ 3 2 hours
Job 2 6 ÷ 3 2 hours
Job 3 6 ÷ 3 2 hours

Net time allocation key

The following table illustrates the formula for calculating allocated time. Here is the formula: Calculated time per reporting = Bundle time ÷ Number of jobs

Example 09:00–10:00 (1 hour) 10:00–11:00 (1 hour) 11:00–13:00 (2 hours) 13:00–15:00 (2 hours) Allocated time
Number of jobs in the bundle 1 3 2 1 Not applicable
Job 1 1 ÷ 1 = 1 hour 1 ÷ 3 = 0.33 hour Not applicable Not applicable 1.33 hours
Job 2 Not applicable 1 ÷ 3 = 0.33 hour 2 ÷ 2 = 1 hour Not applicable 1.33 hours
Job 3 Not applicable 1 ÷ 3 = 0.33 hour 2 ÷ 2 = 1 hour 2 ÷ 1 = 2 hours 3.33 hours

Real time allocation key

If you want production costs to be calculated based on real costs, you must clear the Cost category option on the Production order defaults page. The following table illustrates the formula for calculating allocated time. Here is the formula: Actual time per job = Actual time in bundle

Job Actual time
Job 1 2 hours
Job 2 3 hours
Job 3 5 hours

Consider the three jobs that are performed by a worker who has an hourly wage of USD 12.00. No overtime bonus or premium was earned in the time that was spent on the jobs. The worker worked on the three bundled jobs for a total of six hours. Therefore, the salary cost is 6 × USD 12.00 = USD 72.00. When you use real-time allocation, the cost per hour is recalculated by using the factor from the Net time formula. The actual time that was spent on each job is then transferred together with the corrected cost price per hour. In the example, six hours are spent, although 10 hours were allocated. The following table illustrates the formula for calculating cost. Here is the formula: Cost per hour = (Total bundle time per job (Net time) ÷ Actual time per job) × Standard cost price per hour

Job Calculation of corrected cost per hour Corrected cost per hour Allocated time Total cost of job
Job 1 (1.33 ÷ 2) × USD 12.00 USD 8.00 2 hours USD 16.00
Job 2 (1.33 ÷ 3) × USD 12.00 USD 5.33 3 hours USD 16.00
Job 3 (3.33 ÷ 5) × USD 12.00 USD 8.00 5 hours USD 40.00

The corrected cost per hour and the job time are posted in a production journal. Note: If you select the Cost category option on the General tab on the Production order defaults page, the actual time for each job is transferred to a production journal, where the cost is applied to the cost category of the specific job.