question

LucineideVieira-8915 avatar image
0 Votes"
LucineideVieira-8915 asked emilyhua-msft answered

Can I remove decimals from Resource Usage view?

What is the criteria of MSProject 2013 to caculate the distribution of hours in Resource Usage view? Can I remove the decimals?

office-online-server-general
· 1
5 |1600 characters needed characters left characters exceeded

Up to 10 attachments (including images) can be used with a maximum of 3.0 MiB each and 30.0 MiB total.

Adding the closest teams/tags to assist.

0 Votes 0 ·

1 Answer

emilyhua-msft avatar image
0 Votes"
emilyhua-msft answered

@LucineideVieira-8915
I do not think you may remove decimals from Resource Usage view directly.
It's recommended to refer to the thread "Duration decimals", and try to convert time units from hours to minutes.

81902-untitled1.png

Hope the information could be helpful.


If an Answer is helpful, please click "Accept Answer" and upvote it.
Note: Please follow the steps in our documentation to enable e-mail notifications if you want to receive the related email notification for this thread.