HI!
I have Project Server 2019. I have Project and tasks in it.
I have Resource assignments on Tasks.
The Resource is user1 and Resources Assignments owner by default is user2.
So the Assignments owner is user2 (but the resource is user1).
The Single Entry Mode (SEM) is active.
User2 has full rights.
Why???
- user2 see the assignments of user1 on Tasks page
- but user2 don't see the assignments of user1 on Timesheet page
- and user1 don't see own assignments on Timesheet page too