Hello!
We are currently deploying Dynamics Project Operations and are trying to add multiple staff to 1 task and split hours asymmetrically. For example, the total effort of the task is 20 hours but staff member A should have 15 hours and staff member B should have 5 hours. However, the system is automatically just splitting 10 and 10. Is there a way to edit this? Our projects are fixed effort.
I appreciate your time and help!