in a chain of linked tasks when one deactivates a task and the option to "automatically link inserted or moved tasks" is active in Project Professional, if the task is a milestone, the circuit is not rescheduled, but if it is a task with duration greater than 0 if you reprogram. In previous versions of project if rescheduling is done. Is it a Project problem or is it a type of programming in the tool ?. Thanks.