One Day Duration Task Finishes on Day Two

I've created a blank project and a single task in the plan... no resources assigned, no predecessors, no nothing. The task has a one day duration but finishes on the day following the task start date.

I've tried adjusting the working time in the Options> Schedule... i've tried changing the scheduling type... I've tried associating the Standard Calendar with the task. Nothing I do will make my task finish on the same day it starts.... what am I missing?

office-itpro
5 |1600 characters needed characters left characters exceeded

Up to 10 attachments (including images) can be used with a maximum of 3.0 MiB each and 30.0 MiB total.

1 Answer

emilyhua-msft avatar image
0 Votes"
emilyhua-msft answered emilyhua-msft commented

@SimonTaylor-9687

As your issue is more realted to Project which is not supported on Q&A forum currently, to better help you, I would suggest you post a new thread on Tech Community.
Tech Community --- Porject
Thanks for your understanding.

I personally suggest double-click Project icon, create a blank project from app, go to File > Options > General > Choose one date format includes the time.
128536-image.png

Then create a task with 1 day Durationto to check the start and finish time. Please ensuer the work time is the same as the settings in Schedule.
128553-image.png


If an Answer is helpful, please click "Accept Answer" and upvote it.
Note: Please follow the steps in our documentation to enable e-mail notifications if you want to receive the related email notification for this thread.


image.png (16.5 KiB)
image.png (70.2 KiB)
· 1
5 |1600 characters needed characters left characters exceeded

Up to 10 attachments (including images) can be used with a maximum of 3.0 MiB each and 30.0 MiB total.

@SimonTaylor-9687
Please check whether my information is helpful.