Project Server 2019 - Clear Basline Not Working Correctly

Dears,
We have migrated from Project Server 2013, and all features are working fine, but we have a strange issue in clear baseline feature on the migrated projects only

The issue symptom as following (after using clear baseline):
MS Project Client and the web scheduling are indicating that the baseline is cleared.

The database table are not updated with the clear baseline action, the below tables has an issue:

  1. MSP_Task_Baseline still contains some records for the project for the deleted baseline with active state (including Task 0).

  2. MSP_Task_Baseline_Shadow contains some records for the deleted baseline.

Please advice are we missing something here, or it is a bug.

Thanks & Regards



not-supported
· 1
5 |1600 characters needed characters left characters exceeded

Up to 10 attachments (including images) can be used with a maximum of 3.0 MiB each and 30.0 MiB total.

@AhmedAmin-4768,

Project server and Project Online is currently not supported in Microsoft Q&A.

You can post your question in Microsoft Project Community. The experts there will be willing to provide decent help for your question.


0 Votes 0 ·

1 Answer

DSPatrick avatar image
0 Votes"
DSPatrick answered

The product group for Project actively monitors questions over at
https://techcommunity.microsoft.com/t5/project/ct-p/Project
https://answers.microsoft.com/en-us/msoffice/forum/msoffice_project

--please don't forget to Accept as answer if the reply is helpful--