Hi all,
Got a question regarding our annual DR test, first time in Azure.
We've got 5 scenarios but the main ones are migrating to secondary location from primary (prestaged), test conditions and then migrate back and confirm all data intact and working.
The going back is causing us issues as we'd like to keep the original VMs intact (as much as possible) so after the test we can bring them back up easily.
What is the best way of going about this test to make sure:
- it's successfull
- we can roll back easily and don't need to rebuild VMs or anything like that
- our firewall rules (hub&spoke, protected hub) are in place if we use new VMs instead (DR policy perhaps?)
thanks!