If you have known issues you want to track, you can do so by defining an impediment (Scrum) or issue (Agile or CMMI). Impediments and issues represent unplanned activities. Resolving them requires more work beyond what's tracked for actual requirements. Use the impediment work item type to help you track and manage these issues until you can resolve and close them.

Don't confuse impediments with bugs. You track impediments that may cause problems with delivering one or more requirements. For example, you may have to fix feature ambiguity, personnel or resource issues, problems with environments, or other risks that influence scope, quality, or schedule. Other issues that deserve tracking are decisions that require several stakeholders or product teams to weigh in on.

Important

Issues and Impediments discussed in this article are defined for projects created with the Agile, Scrum, or CMMI process. By default, these work item types don't appear on the product backlog or taskboard.

If your project was created using the Basic process, which tracks work using Epics, Issues, and Tasks, then you track Issues using the product backlog. For more information, see Track issues and tasks.

In this article you'll learn:

  • When to use issues versus tasks
  • How to capture issues or impediments as a work item
  • Add issues or impediments to your product backlog
  • When to use issues versus tasks
  • How to capture issues or impediments as a work item

Prerequisites

  • You must be added to a project.
  • To view or modify work items, you must have your View work items in this node and Edit work items in this node permissions set to Allow. By default, the Contributors group has this permission set. For more information, see Set permissions and access for work tracking.
  • To add new tags to add to work items, you must have Basic access or higher and have the project-level Create new tag definition permissions set to Allow. By default, the Contributors group has this permission set. Even if the permission is explicitly set for a Stakeholder, they don't have permission to add new tags, as they're prohibited through their access level. For more information, see Stakeholder access quick reference.
  • All project members, even members in the Readers group, can send emails containing work items.
  • You must be added to a project.
  • To view or modify work items, you must have your View work items in this node and Edit work items in this node permissions set to Allow. By default, the Contributors group has this permission set. For more information, see Set permissions and access for work tracking.
  • To add new tags to add to work items, you must have Basic access or higher and have the project-level Create new tag definition permissions set to Allow. By default, the Contributors group has this permission set. Even if the permission is explicitly set for a Stakeholder, they don't have permission to add new tags, as they're prohibited through their access level. For more information, see Stakeholder access quick reference.
  • All project members, even members in the Readers group, can send emails containing work items.

Note

The images you see from your web portal may differ from the images you see in this article. These differences result from updates made to your web app, options that you or your admin have enabled, and which process was chosen when creating your project—Agile, Basic, Scrum, or CMMI. The Basic process is available with Azure DevOps Server 2019 Update 1 and later versions.

Define a task

You use issues or impediments to track items that may block work from getting done. In general, you link these items to user stories or other work items using a Related link type.

Define tasks when you want to create a checklist of tasks. You can also define tasks if you use Scrum methods and track work using the Remaining Work field. By linking requirement work item types to tasks using the Parent-Child link type, the tasks appear on the taskboard for each linked user story.

Note

If your project collection uses the On-premises XML process model to customize work tracking, you can enable work item types that you add to the Task Category to appear as a checklist on your product Kanban board. To learn how, see Set up your backlogs and boards, Customize your Kanban Board checklist items.

If you want to add these work item types to a backlog, see Customize your backlogs or boards.

Add an issue or impediment

Open Boards>Work Items, and choose the plus icon, and then select from the New work item menu of options.

Screenshot to add an Impediment from the New Work Item list.

Choose the pin icon to have it show up within the add drop down menu.

Customize issue tracking

For most work item types, you can add fields, change the workflow, add custom rules, and add custom pages to the work item form. You can also add custom work item types. For more information, see Customize an inheritance process.

For most work item types, you can add fields, change the workflow, add custom rules, and add custom pages to the work item form. You can also add custom work item types. For more information, see Customize an inheritance process or Customize the On-premises XML process model depending on the process model used by your project.

Issues and impediments don't appear on your backlog by default. Instead, you track them using queries. To track them on a backlog, see the next section, Add issues or impediments to your product backlog.

Impediments and issues don't appear on your backlog. Instead, you track them using queries. They only appear on your backlog if your project is customized using the On-premises XML process model. For more information, see Customize the On-premises XML process model.

Add issues or impediments to your product backlog

If you want to track issues or impediments along with your requirements or a portfolio backlog, you can track them by adding them to your custom Inherited process. For more information, see Customize your backlogs or boards (Inheritance process).