Activate a production flow version

Note

We will not be accepting edits to this topic, because it is generated from a business process in Lifecycle Services.

Before kanban jobs can be created and activities can be processed for a production flow version, you should activate the version. As a best practice, activate the version before its effective start date and time expire. To complete this task, you must have a production flow version that has the Draft status in order to activate the version.

Find and activate a production flow version

  1. Go to Production flows.
  2. In the list, find and select the desired record.
    • Select a production flow version that has Draft in the Plan status field.
  3. In the list, click the link in the selected row.
  4. In the list, find and select the desired record.
    • Select a production flow version that has Draft in the Plan status field.
  5. Click Activate.
  6. Click OK.