MoveRemainingStartsBack Element

Indicates whether the beginning of remaining portions of tasks scheduled to begin after the status date, but begun early, should be moved back to the status date.

<MoveRemainingStartsBack>
  BooleanValue
</MoveRemainingStartsBack>

Parent Elements

Project

Occurrences

Minimum: 0

Maximum: 1

Text Value

A text value of type boolean is required.

Value

Description

0

False

1

True

Remarks

The MoveRemainingStartsBack element has a rounding error. The internal work value has eight digits; the work value loses 0.001 seconds for every minute, causing a rounding error.