Task.Baseline10BudgetCost Property

Project Developer Reference

Returns or sets the baseline10 budget cost for the rollup calculated value of all the cost resources within the project. Applies only to the Project Summary Task.Task. Read/write Variant.

Syntax

expression.Baseline10BudgetCost

expression   A variable that represents a Task object.

Return Value
Variant

See Also