ProjectDataSet.TaskRow.TASK_ACT_DUR Property

Task actual duration is the span of actual working time for a task so far, based on the scheduled duration and current remaining work or percentage of work complete.

Namespace:  WebSvcProject
Assembly:  ProjectServerWebServices (in ProjectServerWebServices.dll)

Syntax

'Declaration
Public Property TASK_ACT_DUR As Integer
    Get
    Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As Integer

value = instance.TASK_ACT_DUR

instance.TASK_ACT_DUR = value
public int TASK_ACT_DUR { get; set; }

Property Value

Type: System.Int32

Remarks

Read-only.

Duration is indicated in tenths of minutes. A value of 100 indicates 10 minutes.

See Also

Reference

ProjectDataSet.TaskRow Class

ProjectDataSet.TaskRow Members

WebSvcProject Namespace