PS.CalendarException object (ps.js)
Represents a difference (an exception) from the base calendar.
Applies to: Project Professional 2013 | Project Server 2013
PS.CalendarException
Remarks
A calendar exception is an instance in which a task or resource calendar differs from the project calendar. For example, if the project calendar shows 9 am to 5 pm working time Monday through Friday, a calendar exception for one resource might be Tuesday working time from noon to 7 pm.
Members
Methods
The CalendarException object has the following methods.
Method |
Description |
---|---|
This member is reserved for internal use and is not intended to be used directly from your code. |
Properties
The CalendarException object has the following properties.
Property |
Description |
---|---|