Assignment.Peak 屬性 (Project)

取得工作分派的資源單位最大數目。 唯讀 Variant

語法

expressionPeak

表達 代表 Assignment 物件的變數。

範例

下列範例會尋找已分派的資源單位數目超過特定值的任何工作分派。

Sub FindOverassigned() 
 Dim T As Task, A As Assignment 
 Dim TooMany As Double, Results As String 
 
 TooMany = InputBox("Enter maximum allowed units per assignment: ") 
 
 For Each T In ActiveProject.Tasks 
 If Not (T Is Nothing) Then 
 For Each A In T.Assignments 
 If A.Peak > TooMany Then 
 Results = Results & T.Name & ": " & A.ResourceName & vbCrLf 
 End If 
 Next A 
 If Results <> "" Then MsgBox "The following resources are " & _ 
 "assigned more than " & TooMany & " units:" & vbCrLf & Results 
 Results = "" 
 End If 
 Next T 
 
End Sub

支援和意見反應

有關於 Office VBA 或這份文件的問題或意見反應嗎? 如需取得支援服務並提供意見反應的相關指導,請參閱 Office VBA 支援與意見反應