Project) (Assignment.PercentWorkComplete 屬性

取得或設定完成工作分派的工時百分比。 讀取/寫入 Variant

語法

expressionPercentWorkComplete

表達 代表 Assignment 物件的變數。

範例

下列範例會將工時完成百分比大於使用者指定百分比將使用中專案內每個任務 Marked 屬性設定為 True

Sub MarkTasks() 
 
 Dim T As Task ' Task object used in For Each loop 
 Dim Entry As String ' Percentage entered by user 
 
 ' Prompt user for a percentage. 
 Entry = InputBox$("Mark tasks that exceed what percentage of work complete? (0-100)") 
 
 If Not IsNumeric(Entry) Then 
 MsgBox ("Please enter a number only.") 
 Exit Sub 
 ElseIf Entry < 0 Or Entry > 100 Then 
 MsgBox ("You did not enter a percentage from 0 to 100.") 
 Exit Sub 
 End If 
 
 ' Mark tasks with percentage of work complete greater than user entry. 
 For Each T In ActiveProject.Tasks 
 If T.PercentWorkComplete > Val(Entry) Then 
 T.Marked = True 
 Else 
 T.Marked = False 
 End If 
 Next T 
 
End Sub

支援和意見反應