Work with primary and secondary routes

Completed

You might define a resource that's considered a bottleneck or restricting on a route as primary on one route and secondary on another route.

The system automatically applies the specified times for the primary operation to the secondary operations. The system manages secondary operations based on the times that are specified for the primary operation.

You can only adjust the time for the secondary operation by changing the Load and the Quantity fields on the Route numbers page. If no simultaneous operations occur on a route, the system sets up all operations as primary.