Organize your backlog and map child work items to parents in Azure Boards

Azure DevOps Services | Azure DevOps Server 2022 - Azure DevOps Server 2019 | TFS 2018

After you've added features or epics to your portfolio backlog, organize your backlog by mapping backlog items. You can quickly add and group items into a hierarchy. And also drill up or down within the hierarchy, reorder and reparent items, and filter hierarchical views.

In this article you'll learn how to:

  • Open your product backlog or portfolio backlog
  • View the tree hierarchy
  • Group backlog items using the Mapping pane
  • Reparent items through dragging or the Change parent option

Note

For more information, see Backlogs, boards, and plans. In case you're not seeing the desired work items on your backlog or board, see Set up your backlogs and boards to configure them according to your preferences.

Prerequisites

When you create a project or a team, backlogs get created automatically. Each team has access to their own product, portfolio, and sprint backlogs.

Prerequisite Description
Project Administrator or Contributor member You must be added to a project as a member of the Contributors or Project Administrators security group.
Stakeholder access To add or modify work items, you must be granted Stakeholder access or higher. Users with Stakeholder access for public projects have full access to backlog and board features, like users with Basic access. For more information, see Stakeholder access quick reference.
Contributor member or Allow perms on To view or modify work items, you must have your View work items in this node and Edit work items in this node permissions set to Allow. By default, the Contributors group has this permission set to Allow. For more information, see Set permissions and access for work tracking.
Defined iterations To use the Planning pane, your team administrator must define iteration (sprint) paths and configure team iterations.
Prerequisite Description
Project Administrator or Contributor member You must be added to a project as a member of the Contributors or Project Administrators security group.
Stakeholder access To add or modify work items, you must be granted Stakeholder access or higher.
Contributor member or Allow perms on To view or modify work items, you must have your View work items in this node and Edit work items in this node permissions set to Allow. By default, the Contributors group has this permission set to Allow. For more information, see Set permissions and access for work tracking.
Defined iterations To use the Planning pane, your team administrator must define iteration (sprint) paths and configure team iterations.

Note

Stakeholder access users for a private project can't drag items to map or reparent them or to assign their sprint.

Note

Stakeholder access users can't drag items to map or reparent them or to assign their sprint.

Open your backlog from the web portal

From your web browser, open your product backlog.

  1. (1) Check that you've selected the right project, (2) choose Boards>Backlogs, and then (3) select the correct team from the team selector menu.

    Screenshot of Open Work, Backlogs, for a team.

    To select another backlog, open the selector and then choose a different team or select the View Backlog directory option. Or, enter a keyword in the search box to filter the list of team backlogs for the project.

    Screenshot of Choose another team.

    Tip

    Choose the star icon to favorite a team backlog. Favorited artifacts ( favorited icon) appear at the top of the team selector list.

  2. Check that you have selected Stories (for Agile), Issues (for Basic), Backlog items (for Scrum), or Requirements (for CMMI) as the backlog level.

    Screenshot of Choose product backlog level, Backlog items, Stories, or Requirements.

  3. (Optional) To choose which columns should display and in what order, choose the actions icon and select Column options. For more information, see Change column options.

    Screenshot of Open Column Options.

  1. (1) Check that you've selected the right project, (2) choose Boards>Backlogs, and then (3) select the correct team from the team selector menu.

    Screenshot of Open Work, Backlogs, for a team, on-premises version.

    To choose another team, open the selector and select a different team or choose the Browse all backlogs option. Or, you can enter a keyword in the search box to filter the list of team backlogs for the project.

    Screenshot of Choose another team, on-premises version.

    Tip

    Choose the star icon to favorite a team backlog. Favorited artifacts ( favorited icon) appear at the top of the team selector list.

  2. Check that you have selected Backlog items (for Scrum), Stories (for Agile), or Requirements (for CMMI) as the backlog level.

    Screenshot of Choose product backlog level, Backlog items, Stories, or Requirements, on-premises version.

  3. (Optional) To choose which columns should display and in what order, choose the actions icon and select Column options. For more information, see Change column options.

    Screenshot of Open Column Options, on-premises version.

From your web browser, open your team's product backlog. (1) Select the team from the project/team selector, choose (2) Work, (3) Backlogs, and then (4) the product backlog, which is Backlog items (for Scrum), Stories (for Agile), or Requirements (for CMMI).

Screenshot of Open the Boards, Backlogs page, TFS-2018 version.

To choose another team, open the project/team selector and select a different team or choose the Browse option.

Screenshot of Choose another team, TFS-2018 version.

Note

The images you see from your web portal may differ from the images you see in this article. These differences result from updates made to your web app, options that you or your admin have enabled, and which process was chosen when creating your project—Agile, Basic, Scrum, or CMMI. The Basic process is available with Azure DevOps Server 2019 Update 1 and later versions.

Show parent tasks and expand the tree hierarchy

You can set various options to view backlog work items using the View options menu. To learn which options to set based on the tasks you want to accomplish, see Configure your backlog view.

  1. To view Parents or a tree hierarchy, choose the view options icon and slide Parents to On.

    Screenshot of Boards, Backlogs, Open View options and choose Parents on, cloud version.

    The hierarchical view displays. From this view, you can reparent items by dragging a child item to a new parent.

    Screenshot of Backlogs Hierarchical view, cloud version.

  2. Use the Expand and Collapse icons to expand or collapse one level of the hierarchy.

    Screenshot of expand and collapse icons, cloud version.

You can set various options to view backlog work items using the View options menu. To learn which options to set based on the tasks you want to accomplish, see Configure your backlog view.

  1. To view Parents or a tree hierarchy, choose View options and slide Parents to On.

    Screenshot of Boards, Backlogs, Open view options and choose Parents on.

    The hierarchical view displays. From this view, you can reparent items by dragging a child item to a new parent.

    Screenshot of Backlogs Hierarchical view.

  2. Use the Expand and Collapse icons to expand or collapse one level of the hierarchy.

    Screenshot of expand and collapse icons.

From the product backlog page, set Parents to Show when you want to drill up or down within the hierarchy. You can also drag items to reparent items from this view.

Hierarchical view of backlogs

Use the Expand and Collapse icons to expand or collapse one level of the hierarchy.

Collapsed hierarchical view

Map items to group them under a feature or epic

If you've already created your backlog, and now you want to organize it, you can do that most easily by mapping child items to parents.

  1. Choose View options and select Mapping.

    Screenshot of View Options, Mapping enabled, cloud version.

    The Mapping pane displays immediately.

  2. Find Unparented backlog items that may appear at the end of the parented set of backlog items. Parents must be turned on in view options.

    Screenshot of Map unparented items to a feature, cloud version.

  3. To map features to epics, select the Features backlog from the backlog selector. The Epics Mapping pane automatically displays.

  1. Choose View options and select Mapping.

    Screenshot of View Options, Mapping enabled.

    The Mapping pane displays immediately.

  2. Find Unparented backlog items that may appear at the end of the parented set of backlog items. Parents must be turned on in view options.

    Screenshot of Map unparented items to a feature.

  3. To map features to epics, select the Features backlog from the backlog selector. The Epics Mapping pane automatically displays.

To map a backlog item under a feature, you first turn on mapping from your backlog (Backlog items, Stories, or Requirements). Next, find the Unparented backlog items group by turning the Parents control to Show. Unparented backlog items appear at the end of the parented set of backlog items.

Drag items that are currently unparented to the feature under which they belong. Also, you can drag a backlog item to a different feature to change its parent. This mapping creates parent-child links from feature to user stories, which is captured in the Links tab icon (links) tab.

Screenshot of Map a backlog item to a portfolio backlog work item.

You can multi-select backlog and sprint backlog items in the same way as you multi-select items from query results.

It's the same process to map features to epics. From the Features backlog, drag features to an epic listed under the mapping pane.

Change the parent task and reorder items

When you need to change the order or grouping, drag the item to its new location.

You can reparent an item using the mapping pane, or drag it within the hierarchy to change its parent.

Reparent or reorder work items on a backlog

You can only reparent backlog items under other features, and features under other epics.

Also, to change an item's priority within a group, drag the item up or down within its hierarchical group. Reordering from a portfolio backlog works the same as when you moved items into priority order on your product backlog.

Limitations on reordering backlog items owned by other teams

If you find you can't reorder a backlog item, check whether the info icon appears in the first column as shown in the following image.

Limitations on reordering multi-team backlog items

You can reparent items owned by other teams, but you can't reorder items owned by other teams. For more information, see Backlogs, portfolios, and Agile project management, Work with multi-team ownership of backlog items.

Change a parent of multiple backlog items

From a product or portfolio backlog, you can multi-select several work items and choose Change parent… to link the items to a parent work item.

Screenshot of Change parent menu option of several backlog items, cloud version

Screenshot of Change parent menu option of several backlog items.

Add portfolio backlogs and boards

To add a portfolio backlog or board, customize your process, add new work item types, and then configuring your backlogs and boards. You can also add or modify the fields defined for a work item type (WIT) or add a custom WIT. For more information, see Customize an inheritance process and Customize your backlogs or boards (Inheritance process).

To add a portfolio backlog or board, either customize your inherited process or modify your XML definition files. You can also add or modify the fields defined for a work item type (WIT) or add a custom WIT. For more information, see the following articles based on the process model used to update your project:

Inheritance process model:

On-premises XML process model:

To add a portfolio backlog or board, define more work item types, and then customize your process configuration. You can also add or modify the fields defined for a work item type (WIT) or add a custom WIT. For more information, see Customize the On-premises XML process model and Add a portfolio backlog level.

Display rollup progress counts, or totals

Product and portfolio backlogs support rollup columns. You can add one or more rollup columns to display progress bars, counts of descendant work items, or totals of select numeric fields. Your settings persist for each page that you customize and are only valid for your views.

  • Progress bars indicate the percentage of descendant items within a hierarchy that are closed or completed.
  • Counts display the total number of descendant items.
  • Totals provide a sum of numeric fields, such as Effort, Story Points, Completed Work, or Remaining Work of descendant items.

The following example shows progress bars for a portfolio backlog.

Screenshot example of epic, feature, and user stories progress.