Dependency Timeline

The Dependency Timeline feature is in Beta. The Timeline is designed to provide clear sequencing of dependencies across months.

Features

  • Red arrows highlight when the sequencing is out of order and a predecessor is scheduled to be complete after a successor
  • The left-hand colored bar designates the state of each item
  • Hover over an item to see a detailed card or double click to open an individual work item
  • Right clicking of an item to reassign it to a new iteration

Screenshot of Timeline.

In order for the timeline to function correctly Iterations must have dates assigned