This procedure shows how to set up a project resource. This task uses the USMF data set.
- Go to Project management and accounting > Project resources > Resources list.
- Click New resource.
- In the Worker field, enter or select a value.
- In the Calendar field, enter or select a value.
- In the Period code field, enter or select a value.
- Click Create.
- Click Cost prices.
- Click Cost price - hour.
- Click New.
- In the Effective date field, enter a date.
- In the Cost price field, enter a number.
- Click Save.
- Close the page.
- Click Sales prices.
- Click Sales price - hour.
- Click New.
- In the Effective date field, enter a date.
- In the Pricing field, enter a number.
- In the Valid for field, select an option.
- Click Save.
- Close the page.