Set up project resource information

This procedure shows how to set up a project resource. This task uses the USMF data set.

  1. Go to Project management and accounting > Project resources > Resources list.
  2. Click New resource.
  3. In the Worker field, enter or select a value.
  4. In the Calendar field, enter or select a value.
  5. In the Period code field, enter or select a value.
  6. Click Create.
  7. Click Cost prices.
  8. Click Cost price - hour.
  9. Click New.
  10. In the Effective date field, enter a date.
  11. In the Cost price field, enter a number.
  12. Click Save.
  13. Close the page.
  14. Click Sales prices.
  15. Click Sales price - hour.
  16. Click New.
  17. In the Effective date field, enter a date.
  18. In the Pricing field, enter a number.
  19. In the Valid for field, select an option.
  20. Click Save.
  21. Close the page.