ActualStartDrivers.TotalDetectedCount Property

Project Developer Reference

Returns the actual number of CalendarStart drivers. Read-only Long.

Syntax

expression.TotalDetectedCount

expression   A variable that represents an ActualStartDrivers object.

Return Value
Long

Remarks
Actual Start Drivers are assignments that are affecting the start date of a task because they have actual work on the first day of the task.

Example

The following example displays TotalDetectedCount for each task in the active project. The example assumes there are no more than five assignments whose start dates are the same as the task's start date.

Visual Basic for Applications
  Sub b()
    Dim T As Task
    Dim count As Integer
    For Each T In ActiveProject.Tasks
        If T.RecalcFlags = 1 Then
            MsgBox (T.StartDriver.ActualStartDrivers.TotalDetectedCount)
        End If
    Next T
End Sub