ProjectDataSet.TaskRow.TASK_EARLY_FINISH property

Specifies the earliest possible date on which the task can finish.

Namespace:  WebSvcStatusing
Assembly:  ProjectServerServices (in ProjectServerServices.dll)

Syntax

'Declaration
Public Property TASK_EARLY_FINISH As DateTime
    Get
    Set
'Usage
Dim instance As ProjectDataSet.TaskRow
Dim value As DateTime

value = instance.TASK_EARLY_FINISH

instance.TASK_EARLY_FINISH = value
public DateTime TASK_EARLY_FINISH { get; set; }

Property value

Type: System.DateTime

Remarks

Read-only. The earliest date that a task can possibly finish, based on early finish dates of predecessor tasks and successor tasks, other constraints, and any leveling delay.