PS.StandardRateFormat enumeration (ps.js)
Specifies the time unit of the resource rate; that is, the rate per time unit, such as dollars per hour.
Applies to: Project Professional 2013 | Project Server 2013
PS.StandardRateFormat
Members
The StandardRateFormat enumeration has the following members.
Member |
Value |
Description |
---|---|---|
minute |
1 |
The resource rate is per minute. |
hour |
2 |
The resource rate is per hour. |
day |
3 |
The resource rate is per day. |
week |
4 |
The resource rate is per week. |
month |
5 |
The resource rate is per month. |
year |
7 |
The resource rate is per year. |
material |
8 |
The resource is a material; it does not have a rate per time unit. |
Remarks
StandardRateFormat constants can be used to compare with or set the following properties: