On-premises implementation - test, deploy, and operate

Completed

This unit is a summary of the test and deploy phases of an implementation of Finance + Operations (on-premises). Many of the steps are the same as the cloud implementation explained earlier in this module, and will therefore reference that information.

Test

1. Create an on-premises connector

To deploy an on-premises instance from Lifecycle Services, you must set up an on-premises connector. To set up the connector, go to Project Settings, select the On-premises Connectors tab, and then follow the instructions.

2. Deploy sandbox environment

Same as cloud implementation

3. Testing and sign-off

Same as cloud implementation

4. Monitor system health

Always monitor your system health, as with the cloud implementation.

5. Triage bugs

Same as cloud implementation

6. Support tickets

Same as cloud implementation

7. Priority bugs closed

Same as cloud implementation

8. Gold build sign-off

Same as cloud implementation

9. Performance testing sign-off

Same as cloud implementation

Deploy

1. Create an on-premises connector

See the instructions in the Test section above.

2. Deploy a production environment

After you have a gold build identified, and all prerequisites are met, you can begin to work on the Provisioning checklist. This checklist must be complete before you can deploy a production environment using Lifecycle Services.

3. Perform mock cutover

To ensure environment, data, and code packages are successful, a mock cutover must be performed.

4. Monitor system health

Monitor your system health at all times.

5. Perform Go-live health check

All project team members must participate in a Go-live health check to verify that the system is operating as expected.

Operate

Support tickets

You can create a support ticket with Microsoft by using the support service in Lifecycle Services.